Understanding no-budget-impact, pending, billable, executed, and void changes

Change status and financial timing answer different questions.

Project TeamDesktop WebVerified July 24, 2026

Change status and financial timing answer different questions.

Best for: Project managers and accountants · Outcome: Interpret change amounts correctly in contracts and reports.

  • No budget impact describes the Change Event's financial intent.
  • Pending generally means a CO is not executed and has no Billable On date.
  • Billable On allows the change to affect billable reporting separately from signature completion.
  • Fully Executed completes the contract status flow and creates the related SOV effects.
  • Void keeps the record in history without treating it as active.

Executing a CO sets execution and billing information and creates SOV lines. A billable Prime CO can create and lock its Budget Modification.

Do not mark a change executed merely to make it appear in a report. Use the pending-CO report option or Billable On behavior according to the project's actual accounting policy.