The 60-second RFI model
Draft question → Open RFI → Responses → Official Response → Closed RFI → Distribution
Project TeamDesktop WebVerified July 24, 2026
Draft question → Open RFI → Responses → Official Response → Closed RFI → Distribution
- The Manager owns coordination.
- Respondents provide answers. Opening the RFI initially places the ball in their court.
- Subscribers follow activity but are not automatically responsible for the next response.
- The Official Response is an accepted response; accepting and closing are separate decisions.
- Distribution records which question and response attachments were selected and who received the closeout email.